Berwyn strives to keep up to date with infrastructure improvements throughout the City. Along Ogden Avenue, the water main and sewer is in need of improvements. Improvements will include upgrading the water main as well as lead service replacement coordination. Engineers anticipate a preliminary design complete in the Winter of 2024/25. Final engineering, including final plans, specifications and cost estimates was completed in the Winter of 2024. Throughout the project improvement design, the City will meet with stakeholders to inform them of the design and gather feedback and input to incorporate into the final plans. It is anticipated to have construction begin in the Spring of 2025, with a goal of completion in the Fall of 2026.
|