MAKING LONG LASTING CONNECTIONS ON OGDEN AVENUE
|
Only two more blocks of water main installation remain on Ogden Avenue! This work is anticipated to be complete before the end of the month.
Over the last two weeks, the contractor completed a series of critical water main connections at the following locations:
These connections tie newly installed water main into the existing system and activate the new infrastructure into service. Temporary asphalt was also placed at several intersections to restore the roadway and maintain safe travel for motorists while crews prepare the corridor for upcoming roadway restoration. The contractor will continue placing asphalt patches and anticipates this work to be completed by the end of July. As we prepare for another productive summer, please continue to travel with caution throughout the area and support Berwyn's local businesses during construction. |
Archives
|
Spring 2025
Spring 2026
|